21.02.2013

When a shortcut goes wrong

On Monday this week a relatively simple lift went expensively wrong, thanks to a contractor using a smaller crane than the job demanded.

The project involved the installation of a steel foot and cycle bridge weighing around 40 tonnes that will connect the two communities of Hunter Crescent and Lisanelly in Omagh, Northern Ireland.

The project, part of a new Riverside Walk, is costing around £900,000 and is financed by the local council, the department for social development and transport charity Sustrans.

We know that one of the contractors, McLaughlin & Harvey or bridge builder M.Hassons & Sons, approached a number of crane rental companies to carry out the lift, at least one of which recommended that a single 500 tonne crane be used, complete with spreader beams to ensure that the lightweight bridge structure was not subjected to excessive compression stresses during the lift.

However it was decided to carry out a tandem lift instead, using a 350 tonne crane together with a smaller telescopic on the opposite bank.

The bridge was slung with four legs of the chainset attached to the lower chords of the bridge deck. The plan was to lift it just across the river with the 350 tonne crane, then set it down or ‘rest it’ on the concrete support, re-rig it for a tandem lift, by connecting up the smaller crane and then re-jigging the larger crane’s slings so that the two cranes could then lift it into its final position.
Please register to see all images

The bridge is rested and re-rigged for a tandem lift - note the bridge deck chords


Well needless to say all did not go according to plan, the major concerns about keeping the bridge stable while it was re-rigged, or keeping the distribution of the load balanced accurately between the two cranes etc… were not the problem in this case. No it was the rigging of the load that did it, as the bridge was placed onto its mid-lift resting place it buckled horribly. To the point where it could well be a complete ‘write-off’?

The lift had to be abandoned and the bridge returned to its starting point – discussions have already begun about whose fault it is, and surely a good deal of this debate will centre on whether it was a regular crane hire or a contract lift? One thing that seems certain is that those financing it say they will not pay.

A statement from the council said: "Council officials have received an initial briefing from the contractor and have requested a report by the end of the week identifying what happened and outlining the actions proposed to complete the installation of the Bridge. Work on the remaining element of the project is unaffected and it is currently anticipated that the project will be completed on programme.”

Click here to see a video of the lift and local news report

Vertikal Comment

One has to wonder how after all the debates about safety and warnings issued about the risks of tandem lifting, and the need to for proper planning and the use of a hierarchy system of risk assessment a government funded project ignored the lot? On top of this both the bridge builder and contractor make a big deal about safety and are certified as complant to OHSAS 18001.

We know that at least one 500 tonner was available in Ireland on the day of the lift and not working, the contractors were aware that there were several companies in the country that could carry out the lift using a single crane and yet…..whomever was involved in the planning of the project chose to use a method that screamed risk… a tandem lift over a waterway, that involved re-rigging the load halfway through the lift, that entailed men walking across the ‘balanced’ bridge to carry out that rigging surely someone should have said “hang isn’t there an easier way to do this?”

Why is it that good companies that take so much time to put safety statements in place and obtain all the right acreditations ignore it all when it comes to renting a crane?

Well the end result is thankfully not an injury, or pollution of the river from a submerged crane, but just a destroyed bridge that someone will have to pay for. I wonder who?

Comments

dealer205
could have been a case of the 'tail wagging the dog' crane companies telling contractors the 'best way' to do something can sometimes be the best way for the crane company, and not the contractor. was this a contract lift?

Feb 26, 2013

dealer205
costly!!

Feb 26, 2013

lambsy
Once again it seems the main contractor has gone for the perceived cheapest option , there are no crane hire companies in the north of ireland in ownership of a 500 ton crane .
No doubt the extra cost of travel from dublin or cork added too the poor decision making process in this case .
The sad thing about this case is , this company is well known regards training there foremen and engineers in appointed persons , courses , i would say they have more AP s than most civil engineering firms in Ireland yet this type of shoddy managment of crane lifts still continues ?
Just pure luck no one was hurt.

Feb 24, 2013

thomas laganga
lifts like this are done all the time in US. the bridge should of been landed on a falsework that would support the inboard bearing pads while the smaller crane held the load close to its outboard bearing pads (with the smaller crane being in a safe loading area for its load chart. the larger crane would then re-rig at the inboard bearing points and the bridge set at its final resting point. all the while bottom chords are in tension (as the design intends) and no structural damage occurs. just an example of no lift planning or interaction with the bridge fabricator.

Feb 21, 2013