01.09.2021
Custom platforms for channel tunnel
Palfinger has built 16 special rail mounted work platforms for maintenance work on the channel tunnel.
Please register to see all images
The Palfinger PA1500 tunnel maintenance platforms
The Palfinger PA1500 platform was designed and built by Palfinger Rail for its UK partner GOS Tool Engineering. Each unit employs a single scissor mechanism to raise or lower the six metre long platform, which has an overall width of 2.9 metres that can be extended to 4.5 metres by its 1.6 metre lateral slide out extension. The platform capacity is 1,500kg.
Please register to see all images
The large platforms can operate as one thanks a synchronous operation mode
The platforms have been designed on a modular basis for mounting on a range of different chassis but will typically operate as a double unit on a low riding rail wagon. In this configuration the two platforms can be operated independently or simultaneously as a single unit, by selecting the synchronous operation mode on the remote controller.
Please register to see all images
The 1.6 metre lateral slide out extensions take the platform width from 2.9 to 4.5 metres
The tunnel is currently having a new high voltage DC power line installed to transfer power between the UK and France. A risk assessment carried out by Eurotunnel found that the power line was most likely to be damaged by a crane or an access platform during routine maintenance work and thus commissioned a custom made solution that would carry out the work with fewer risks.
In addition to the PA1500 platforms, the order also include two PKR 800 railway cranes, six PR 220 cranes with BB 29 and BB 49 work platform attachment, two PA 200 platforms and other equipment.