07.10.2009
HSE issues Liftlux bulletin
Following an incident in June this year, the UK’s Health & Safety Executive has issued a bulletin insisting that, unless they have already done so, owners of Liftlux Models SL260-25, SL245-25, SL210-25 and 205-25 immediately pull them out of service and carry out a structural inspection of the chassis.
The bulletin is published in full below.
Vertikal Comment
It should be pointed out that only one failure has occurred so far and that on a model SL260-25 in an incident in which no one was hurt.
So far, as far as we know only two or three other units have been found to have cracks and those were relatively minor. Should a failure occur it is almost certainly going to be during platform lift-off or closure, when stresses on the chassis are at their maximum, thus the risk of serious injury is limited.
The manufacturers involved - Manitowoc and JLG contacted all owners of these units very rapidly following the incident and promptly issued a bulletin. In the UK the owners of Liftlux 260/245s have been pooling information and working in a diligent manner to help avoid any repetition and to learn of each others findings.
Why then the HSE feel that it had to issue such a public bulletin itself, prior to the completion of its investigation, is a mystery. Particularly when it has in the past seemed prepared to 'sit on' such information in the case of a tower crane fatality or near miss.
It is also curious as to why it had to include other ranges of Liftlux scissors that have not been affected. It might as well have included all scissor lifts in the bulletin.
We have been strong advocates of the HSE issuing such information promptly and not sitting on it just in case it might decide to launch a prosecution. Such action can save lives, although to start doing it with this case, where there has been no injury and the risks appear low seems absurd.
The HSE Bulletin
Failures of Liftlux Scissor lifts Models SL260-25 and SL245-25
Safety Alert - Liftlux Models SL260-25, SL245-25, SL210-25 and 205-25
Introduction
The purpose of this Information Bulletin is to alert employers and employees about recent structural failures of the main support structure (chassis) on Liftlux models SL260-25 and SL245-25 scissor lifts. This information is being provided in advance of the conclusion of HSE’s investigations so that the industry can take prompt action to prevent a recurrence.
During the incidents cracks propagated across the entire width of the chasses causing the machines to collapse as shown in Figure 1. Following these incidents a number of machines of the same models but different ages were withdrawn from service and visually inspected in the same area of the chassis. On many of the machines cracks were found that could potentially have led to similar failures.
No similar failures have yet been identified in Liftlux models 210-25 and 205-25, although because these models are of a similar design, they should also be subject to the action detailed below.
Background
The size of the cracks found on the machines appears to be proportional to the registered hours of use, i.e. the largest cracks were found on the machines with the highest recorded service hours. This is indicative of a fatigue failure which occurs when cyclic stresses cause a small crack to propagate (grow) until it reaches a critical size. If undetected this could result in a structural failure of the chassis when the critical size (currently unknown) is reached.
Preliminary examinations suggest that the fatigue cracks might have initiated in an area where several features of the chassis have been welded together on the underside of the machine as shown in Figure 3 & 4.
Fatigue is then thought to have been induced by the constant cycling of the ram each time the platform is raised and lowered causing the crack to grow. The cracks showed signs of growing into the horizontal area at the side of the machine (near the starting batteries) as shown in Figure 2.
In the later stages crack growth is believed to progress into the vertical section of chassis in the area shown in Figure 2. It is also likely that cracking may be present on the opposite side of the machine but this position is hidden by the tank for the hydraulic fluid.
Action to be taken
If you have one of these machines and have not completed the inspection as required by the manufacturers’ bulletins released recently, you should immediately withdraw it from service so that it can be examined by a competent person. The inspection procedure is detailed below:
During examination, extreme care must be taken to ensure that the examination is done safely without a risk to the examiner should the chassis collapse. For example, additional props and supports should be placed under the machine chassis if the examiner needs to gain access beneath it.
1.Park the machine on a firm, level, supporting surface free of overhead obstructions. Ensure the machine is shut down and the key removed.
2.Locate and identify the chassis frame baseplate transverse weld as shown in Figure 3.
3.Visually inspect for signs of weld or parent metal cracks along the entire length of the weld.
4.Replace the key, and prepare the machine for operation in accordance with its Operation & Safety Manual. From the ground controls, elevate the platform approximately 2 metres, shut the machine down and inspect the area indicated in Figure 3 for signs of cracks on both sides of the Scissor Lift.
5.Locate and identify the hydraulic compartment as shown in Figure1.
6.Visually inspect for signs of weld or parent metal cracks, in particular in the area to the left of the starter batteries
7.If any crack or other discrepancy is found, cease operation, remove the scissor lift from service and contact your Liftlux agent or competent person who should be able to advise you on the appropriate course of action to take.
8.Should any further discrepancies be discovered during the accomplishment of this procedure, contact your Liftlux agent or competent person.
If no cracks are detected then employers should determine a suitable interval time for re- examination of these parts of the machine by a competent person between thorough examinations.
Relevant legal references
The Health and Safety at Work etc. Act 1974 especially sections 2 and 3 Lifting Operations and Lifting Equipment Regulations 1998 (LOLER)
Regulation 9(3) of LOLER requires persons in control of lifting equipment to ensure that lifting equipment for lifting persons which is exposed to conditions causing deterioration which is liable to result in dangerous situations is thoroughly examined at least every six months or in accordance with an examination scheme and, if appropriate for the purpose, is inspected by a competent person at suitable intervals between thorough examinations.
Further information is available in “Safe use of Lifting Equipment” Approved Code of Practice and Guidance (L113).
General note
Please pass this information to anyone you think may need it.
Please register to see all images
Fig 1. Scissor lift after catastrophic failure of chassis. Arrow shows hydraulic compartment
Please register to see all images
Fig 2. Hydraulics compartment showing area where catastrophic failure is evident.
Please register to see all images
Fig 3. Showing transverse weld beneath the superstructure. This is at access end of the machine near the cylinder
Please register to see all images
Fig 4 Transverse weld beneath body showing weld failure.