In order to view all images, please register and log in. This will also allow you to comment on our stories and have the option to receive our email alerts. Click here to register
03.01.2025

Mammoet's Amsterdam Bridge Project

Dutch international heavy lift and transport company Mammoet began a five year project to replace five bridges at Amsterdam Centraal Station at the end of last year.

The project involves replacing four steel railway bridges and one concrete bridge on the east side of the station allowing it to handle more trains and passengers. The company is working alongside Dutch civil engineer Dura Vermeer as part of the High Frequency Rail Transport (PHS) Programme, which includes track upgrades and station renovations.
Please register to see all images

A train passing over the bridge and work site


Each bridge is made up of three sections, with overall lengths of 24 to 28 metres and weighing between 173 and 275 tonnes. The sections are being built in the Netherlands by Hollandia and transported to the station via canal/waterways. They travel on flattop barges through the river De Lek and the Lekkanaal, arriving at the Oostertoegang area of the station.

To pass under a low footbridge near the site, the main barge is partially submerged using pontoons filled with water to make the barge sit lower. Once in position, a 90 tonne mobile crane on a temporary bridge removes the pontoons and replaces them with Mammoet’s Self Propelled Modular Transporters (SPMTs).
Please register to see all images

Passing under the footbridge


Mammoet then employs its Mega Jack 300 system to lift the bridge sections to a height of four metres, allowing SPMTs to position a support frame underneath. The sections are then rotated 90 degrees, driven off the barge across steel mats, and placed onto support towers.
Please register to see all images

The SPMTs moving into position


Installation begins with the east section, followed by the west, and finishes with the middle section, which is lifted and installed over the water.
The operation will be carried out almost entirely on water to minimise disruption, with a plan to replace one bridge each year until the project concludes in 2028.
Please register to see all images


Mammoet project manager Leo de Vette said: “We have been involved in this project since 2021 and came up with the approach to install the bridges on water to limit transport movements and disruption in the city centre. This makes it a complex operation because space is limited and there are many steps that must be carefully managed. Every change you make influences something else, and that is a major challenge for this project.”

Dura Vermeer project manager Martin de Ruijter added: “This renovation project will allow more trains to operate from the station and accommodate the growth in passenger numbers. Mammoet’s engineering expertise has proved invaluable, resulting in a solution that has allowed the station to remain operational while the work takes place, minimising disruption to passengers and the city.”

Comments